Planned battery storage projects in Oregon (50 MW and up)

7 planned battery generator rows of 50 MW or more in Oregon, 2,897 MW in total, from the September 2026 EIA-860M workbook; the largest 25 are shown. A plant can be several rows. Refreshed 2026-11-17.

Plant Owner County MW Planned online Status
Sunstone Solar Sunstone Solar, LLC Morrow 1200 2027-12 (L) Regulatory approvals pending. Not under construction
Deschutes Solar and BESS DECH bn, LLC Wasco 1000 2029-11 (L) Regulatory approvals pending. Not under construction
Salmonfly Solar and Storage BrightNight Power Jefferson 247 2029-02 (L) Regulatory approvals pending. Not under construction
Tualatin Battery Energy Storage System TUAL bn, LLC Washington 200 2027-12 (L) Regulatory approvals pending. Not under construction
Biglow Solar Generation and BESS BIGL bn, LLC Sherman 125 2027-12 (L) Regulatory approvals pending. Not under construction
Wheatridge Optimization I Wheatridge Optimization I, LLC Morrow 65 2027-12 (U) Under construction, less than or equal to 50 percent complete
Wheatridge Optimization II Wheatridge Optimization II, LLC Morrow 60 2027-12 (U) Under construction, less than or equal to 50 percent complete

Download CSV ยท All weekly slices

Get this slice as live, filterable data with US Power Plant Pipeline on Apify. Input for this slice:

{
  "inventories": [
    "planned"
  ],
  "states": [
    "OR"
  ],
  "technologies": [
    "Batteries"
  ],
  "minMw": 50,
  "maxResults": 500
}

Source: U.S. Energy Information Administration, Form EIA-860M (public domain). Capacity is preliminary nameplate MW.