Weekly sample pages from public-records data feeds (tenders, grants, power projects)
View the Project on GitHub beingRealFrank/civic-data-feeds-samples
13 planned battery generator rows of 50 MW or more in Colorado, 1,899 MW in total, from the September 2026 EIA-860M workbook; the largest 25 are shown. A plant can be several rows. Refreshed 2026-11-17.
| Plant | Owner | County | MW | Planned online | Status |
|---|---|---|---|---|---|
| Dry Land Prairie Energy Storage | Dry Land Prairie Energy Storage, LLC | Cheyenne | 250 | 2026-12 | (U) Under construction, less than or equal to 50 percent complete |
| South Platte Storage | South Platte Storage, LLC | Morgan | 250 | 2027-06 | (U) Under construction, less than or equal to 50 percent complete |
| Pawnee Solar & BESS | Public Service Co of Colorado | Morgan | 200 | 2027-12 | (U) Under construction, less than or equal to 50 percent complete |
| Morel Energy Storage | Morel Energy Storage LLC | Moffat | 200 | 2030-12 | (T) Regulatory approvals received. Not under construction |
| Spindle BESS | Spindle Battery LLC | Weld | 199 | 2026-12 | (TS) Construction complete, but not yet in commercial operation |
| Fortress 1 | Fortress Solar 1 LLC | Morgan | 150 | 2028-03 | (L) Regulatory approvals pending. Not under construction |
| Carousel Energy Storage, LLC | Carousel Energy Storage, LLC | Kit Carson | 149.6 | 2027-12 | (T) Regulatory approvals received. Not under construction |
| Weld Energy Storage | Weld Energy Storage, LLC | Weld | 100 | 2026-12 | (V) Under construction, more than 50 percent complete |
| Highland Solar I, LLC - (CO) | Highland Solar I, LLC | Pueblo | 100 | 2027-12 | (L) Regulatory approvals pending. Not under construction |
| Drennan Energy Storage | Drennan Energy Storage LLC | El Paso | 100 | 2028-03 | (L) Regulatory approvals pending. Not under construction |
| Grand Valley Solar Generation and BESS | GRVA bn, LLC | Mesa | 100 | 2029-10 | (L) Regulatory approvals pending. Not under construction |
| Sundance (CO) | Cypress Creek Renewables | Elbert | 50 | 2026-10 | (U) Under construction, less than or equal to 50 percent complete |
| Pueblo Airport Generating Station | Black Hills Service Company LLC | Pueblo | 50 | 2027-12 | (L) Regulatory approvals pending. Not under construction |
Download CSV ยท All weekly slices
Get this slice as live, filterable data with US Power Plant Pipeline on Apify. Input for this slice:
{
"inventories": [
"planned"
],
"states": [
"CO"
],
"technologies": [
"Batteries"
],
"minMw": 50,
"maxResults": 500
}
Source: U.S. Energy Information Administration, Form EIA-860M (public domain). Capacity is preliminary nameplate MW.