Planned battery storage projects in Colorado (50 MW and up)

13 planned battery generator rows of 50 MW or more in Colorado, 1,899 MW in total, from the September 2026 EIA-860M workbook; the largest 25 are shown. A plant can be several rows. Refreshed 2026-11-17.

Plant Owner County MW Planned online Status
Dry Land Prairie Energy Storage Dry Land Prairie Energy Storage, LLC Cheyenne 250 2026-12 (U) Under construction, less than or equal to 50 percent complete
South Platte Storage South Platte Storage, LLC Morgan 250 2027-06 (U) Under construction, less than or equal to 50 percent complete
Pawnee Solar & BESS Public Service Co of Colorado Morgan 200 2027-12 (U) Under construction, less than or equal to 50 percent complete
Morel Energy Storage Morel Energy Storage LLC Moffat 200 2030-12 (T) Regulatory approvals received. Not under construction
Spindle BESS Spindle Battery LLC Weld 199 2026-12 (TS) Construction complete, but not yet in commercial operation
Fortress 1 Fortress Solar 1 LLC Morgan 150 2028-03 (L) Regulatory approvals pending. Not under construction
Carousel Energy Storage, LLC Carousel Energy Storage, LLC Kit Carson 149.6 2027-12 (T) Regulatory approvals received. Not under construction
Weld Energy Storage Weld Energy Storage, LLC Weld 100 2026-12 (V) Under construction, more than 50 percent complete
Highland Solar I, LLC - (CO) Highland Solar I, LLC Pueblo 100 2027-12 (L) Regulatory approvals pending. Not under construction
Drennan Energy Storage Drennan Energy Storage LLC El Paso 100 2028-03 (L) Regulatory approvals pending. Not under construction
Grand Valley Solar Generation and BESS GRVA bn, LLC Mesa 100 2029-10 (L) Regulatory approvals pending. Not under construction
Sundance (CO) Cypress Creek Renewables Elbert 50 2026-10 (U) Under construction, less than or equal to 50 percent complete
Pueblo Airport Generating Station Black Hills Service Company LLC Pueblo 50 2027-12 (L) Regulatory approvals pending. Not under construction

Download CSV ยท All weekly slices

Get this slice as live, filterable data with US Power Plant Pipeline on Apify. Input for this slice:

{
  "inventories": [
    "planned"
  ],
  "states": [
    "CO"
  ],
  "technologies": [
    "Batteries"
  ],
  "minMw": 50,
  "maxResults": 500
}

Source: U.S. Energy Information Administration, Form EIA-860M (public domain). Capacity is preliminary nameplate MW.