26 planned battery generator rows of 50 MW or more in Arizona, 6,558 MW in total, from the September 2026 EIA-860M workbook; the largest 25 are shown. A plant can be several rows. Refreshed 2026-11-17.
| Plant | Owner | County | MW | Planned online | Status |
|---|---|---|---|---|---|
| Maricopa Solar | Maricopa Solar | Maricopa | 550 | 2026-12 | (U) Under construction, less than or equal to 50 percent complete |
| Snowflake A Solar and BESS | Clenera DevCo LLC | Navajo | 475 | 2027-08 | (L) Regulatory approvals pending. Not under construction |
| CO Bar Solar and BESS | Clenera DevCo LLC | Coconino | 400 | 2027-12 | (P) Planned for installation, but regulatory approvals not initiated |
| Valley Farms Energy Center | Valley Farms Energy Center, LLC | Pinal | 400 | 2027-12 | (U) Under construction, less than or equal to 50 percent complete |
| Eagle Eye Solar and Storage | EAGL bn, LLC | La Paz | 400 | 2028-05 | (L) Regulatory approvals pending. Not under construction |
| CO Bar D Solar and BESS | Clenera DevCo LLC | Coconino | 394 | 2028-05 | (P) Planned for installation, but regulatory approvals not initiated |
| Pioneer Clean Energy Center | Yuma bn, LLC | Yuma | 300 | 2027-04 | (U) Under construction, less than or equal to 50 percent complete |
| Red Antelope Solar & Energy Storage Farm | 302PN 8me LLC | Coconino | 300 | 2028-05 | (P) Planned for installation, but regulatory approvals not initiated |
| Desert Sand BESS | DESA bn, LLC | Maricopa | 300 | 2028-12 | (L) Regulatory approvals pending. Not under construction |
| THREE SISTERS Solar Generation and BESS | THSI bn, LLC | Pinal | 300 | 2029-04 | (L) Regulatory approvals pending. Not under construction |
| Hashknife Energy Center LLC | Invenergy Services LLC | Navajo | 275 | 2026-11 | (V) Under construction, more than 50 percent complete |
| Sawtooth Solar | EDF Renewables Development, Inc. | Pinal | 250 | 2028-06 | (L) Regulatory approvals pending. Not under construction |
| Romero Energy Center | Romero Energy Center, LLC | Maricopa | 225 | 2027-06 | (U) Under construction, less than or equal to 50 percent complete |
| Romero Energy Center II, LLC | Romero Energy Center II, LLC | Maricopa | 225 | 2028-06 | (U) Under construction, less than or equal to 50 percent complete |
| Atlas VIII | Atlas VIII LLC | La Paz | 210 | 2026-12 | (V) Under construction, more than 50 percent complete |
| CO Bar C Solar and BESS | Clenera DevCo LLC | Coconino | 206 | 2027-08 | (P) Planned for installation, but regulatory approvals not initiated |
| Hashknife Energy Center II LLC | Invenergy Services LLC | Navajo | 200 | 2027-03 | (V) Under construction, more than 50 percent complete |
| Atlas VIII | Atlas VIII LLC | La Paz | 172.4 | 2027-01 | (V) Under construction, more than 50 percent complete |
| Agave | Arizona Public Service Co | Maricopa | 150 | 2026-11 | (TS) Construction complete, but not yet in commercial operation |
| Atlas BESS IV LLC | ATLAS BESS IV, LLC | La Paz | 150 | 2027-03 | (V) Under construction, more than 50 percent complete |
| Selma Energy Center | Selma Energy Center, LLC | Pinal | 150 | 2027-12 | (U) Under construction, less than or equal to 50 percent complete |
| Sierra Luna Energy Storage | Sierra Luna Energy Storage LLC | Maricopa | 150 | 2030-12 | (P) Planned for installation, but regulatory approvals not initiated |
| Kitt Solar | 301AK 8me LLC | Pinal | 100 | 2026-12 | (V) Under construction, more than 50 percent complete |
| White Tank Energy Storage | White Tank Energy Storage LLC | Maricopa | 100 | 2027-04 | (U) Under construction, less than or equal to 50 percent complete |
| Winchester Solar I, LLC | Torch Operating Company, LLC | Cochise | 87.8 | 2027-03 | (V) Under construction, more than 50 percent complete |
Download CSV ยท All weekly slices
Get this slice as live, filterable data with US Power Plant Pipeline on Apify. Input for this slice:
{
"inventories": [
"planned"
],
"states": [
"AZ"
],
"technologies": [
"Batteries"
],
"minMw": 50,
"maxResults": 500
}
Source: U.S. Energy Information Administration, Form EIA-860M (public domain). Capacity is preliminary nameplate MW.